Street Improvement Project Schedule Update - week of Sept. 17

Please be advised of the following work that will take place during the week of Sept. 17, as part of the City of Pittsfield’s 2018 Street Improvement Project.

The schedule is as follows:

Monday, Sept. 17: removal of existing/ installation of new aprons continues on Jason Street (Gale to Roselyn) and Tor Court.

Tuesday, Sept. 18 through Wednesday, Sept. 19: raising structures on Maplewood Avenue.

Wednesday, Sept. 19 – Thursday, Sept. 20: raising structures on Crofut Street.

Thursday, Sept. 20-Friday, Sept. 21: raising structures on McKay Street.

Please note the schedule is subject to change based on weather conditions. The City of Pittsfield thanks you for your patience during this time.