Street Improvement Project Schedule Update - Week of Aug. 13

PITTSFIELD, Mass. – Please be advised of the following work that will take place the week of Aug. 13, as part of the City of Pittsfield’s 2018 Street Improvement Project.

 The schedule is as follows:

 Wednesday, Aug. 15: final pave on Dalton Avenue.

 Thursday, Aug. 16 – Friday, Aug. 17: Milling and miscellaneous repairs on Hubbard Avenue.

During this work, there will be no parking on Dalton Avenue (eastbound lane). Additionally, there will be a single lane closure on Hubbard.

Please note the schedule is subject to change based on weather conditions. The City of Pittsfield thanks you for your patience during this time.