Streetscape Phase 4 Construction Update for March 21-25

Streetscape Phase 4 contractor, Maxymillian, will continue working on the installation light pole bases during Monday, March 21st through Friday, March 25th. Construction work is scheduled to begin at 7:30 a.m.

On Monday, work will begin on the west side of North Street between Bradford and Linden streets.  It will then continue north with the goal of completing the installation of the all the streetlight bases on the west side of North Street up to Madison Avenue.  There is a possibility a few streetlight bases could be installed on the east side of North Street between White Terrace and Maplewood Avenue toward the end of the week.

Small isolated sections of sidewalk will be removed so the area can be prepared for the installation of new streetlight bases.

There will be minimal inconvenience to the businesses, pedestrians and vehicular traffic. At times the work will impact parking spaces. Vehicular traffic will be guided with signs, cones and drums allowing traffic to travel safely to the downtown area.